With regard to the issue of receiving two units of equipment 1312-C-304;1312-C-303
Previously we received a notice from CCSM saying that the equipment 1312-C-304 and 1312-C-303 would be delivered to the site by the night of July 28th ,2016. However , as the port and site road conditions had not been ready then , the date was changed as to the night of August 1st . And then we got the 250 ton crane, excavator, loader, roller and workforce standby for the coming equipment . We waited two nights but the equipment has not arrived yet. Please kindly see the attachment of the time sheet for the two nights.