please somone help me in correcting this letter.
Dear sir,
We would like to ask for compensation in slab pouring concrete work for first floor.
In original plan there were not any gaps, while the gaps that we applied made delay in our schedule, and take a lot of effort in shuttering for both ground floor and Mezzanine.
The amount that deducted in slab payment = 43 m3 * 100 fdj= 4300 fdj, this is fair compensation that we believe.
Best regard,
ค้นหาจากครู ภาษาอังกฤษ หลากหลายคน...
การแก้ไข · 1
0
please somone help me in correcting this letter.
Dear sir,
We would like to ask you for compensation for the concrete slab work that we have done on first floor.
In the original plan there were no gaps, however , the gaps that we applied caused a delay in our schedule and thus, took a lot more effort in shuttering both the ground floor and Mezzanine.
The amount that was deducted in the slab payment = 43 m3 * 100 fdj= 4300 fdj. We believe that this is a fair compensation.
Best regards.